Twenty schools, twenty deadlines
A trust of twenty schools that joined over eight years can hold twenty MIS contracts with twenty end dates. At DfE's briefing on 11 November 2026, officials were direct about which dates matter. Plan backwards from each contract's end, they said, and leave time for requirements, governance, procurement, implementation, training and migration. The framework's planned September 2027 launch is a waypoint on that plan.
What framework suppliers will accept
The briefing set out five commitments every framework supplier will sign up to.
| Commitment | What it means for a trust |
|---|---|
| Control | Schools and trusts remain data controllers. Nothing is shared without their authorisation. |
| Free access | No school pays to reach its own operational or statutory data. |
| Fair connection | Third parties connect through APIs on non-discriminatory terms. Charges above fair use must be transparent and proportionate. |
| Portability | Data can be exported and migrated without technical or contractual barriers. |
| Statutory flows | Statutory and operational data reaches DfE and authorised suppliers at no cost to schools. |
The fifth commitment repays a second reading. It removes a cost, and it also describes a direction of travel. "Operational" is a broader category than the returns a school already files, and the same procurement is exploring how the department might use school data to produce insights of its own. Essays 3 and 4 take that up.
Suppliers will also have to meet technical requirements:
- Core data in a common, machine-readable format.
- APIs wherever a standard connection is feasible.
- Bulk download that the supplier cannot switch off.
- Published API documentation and prices, and a list of every third-party integration marked one-way, two-way or via an aggregator.
- Cooperation with migration, and continued access to data during exit.
- Demonstrations on video and live before award.
Rules already in force
Much of this protection is available now. In July 2026 DfE published eighteen MIS Core Principles1 for any MIS procurement before the framework opens, and says they "will form the basis of the MIS Framework procurement2". The terms most trusts will feel are these:
- Security. Cyber Essentials Plus and/or ISO 27001, or working towards them, with completion by spring 2027 at the latest.
- Prices. Published, including whether each integration is one-way, two-way or via an aggregator.
- Renewal. A contract may renew automatically once, for at most 12 months, and the supplier must give written notice at least six months before the initial term ends.
- Term. Three years at most, including any additional term. Support contracts end with the MIS contract they support.
- Acceptance. Clicking through a portal does not count as agreement.
- Title. "All rights in and to, and title to, School Data will remain with the School."
- Access and exit. Data is available at any time, including during exit, at no additional cost. Systems are API-enabled, and the supplier cooperates on migration.
One clause deserves a line in the budget. Bulk transfers are free "no more than 3 times during a contract year". Beyond that a supplier may charge a reasonable, proportionate cost; on exit, transfer is free. Essay 3 returns to it.
What the Academy Trust Handbook requires
For academy trusts the framework is compulsory. Paragraph 2.30 of the 2026 Handbook3, in force since 1 October 2026, says trusts "must ensure that all Management Information System (MIS) contracts are awarded under DfE's MIS framework as soon as practicable after its launch (planned for September 2027) and in line with expiry of their current contract". Two rules follow.
- Where a contract expires before the framework launches, any extension must be for no more than 12 months. A trust that re-procures instead must include DfE's MIS Core Principles in its requirements.
- Where a contract runs beyond launch, the trust must not use extension options that delay transition.
Local authority-maintained schools are expected to use the framework4, and further education providers may use it.
The compulsion is contested. Sir Jon Coles, chief executive of United Learning, told Tes5 that the department is "vastly exceeding the powers" of the handbook and risks "serious legal challenge", and that he had never met "a requirement to use a specific framework, which doesn't even exist yet". Plan on the basis that paragraph 2.30 applies, because a trust that assumes otherwise and is wrong has no fallback. Treat the mandate as firm for planning and unsettled in public argument.
The timetable
| Milestone | Date |
|---|---|
| Preliminary market engagement closes | 13 November 2026 |
| Invitation to tender | 11 January 2027 |
| Tender submissions due | 22 March 2027 |
| Award | July to August 2027 |
| Framework opens | 1 September 2027 (planned) |
DfE's own pages disagree on the month. The Core Principles guidance refers to the framework being "established in June 2027"; the Handbook, DfE's procurement service and the briefing say September. Plan for September and treat it as provisional.
Where your trust stands
Contracts that end before September 2027. Ask the supplier for a short extension first. DfE told the briefing it is pressing suppliers to offer 12 months, which is also the Handbook's limit. If the supplier refuses, procure a new contract with the Core Principles written in as conditions, and keep it to three years including extensions.
Contracts that end after September 2027. There is time, though less than it looks. Use it for the work procurement depends on: what the trust needs from its data, who decides, and what a good exit looks like. Do not take up extension options that carry you past the point where you could move to the framework.
Schools on different dates. This is the usual case in a trust that has grown by taking on schools. Map every school by supplier, end date, notice period and extension rights, then decide whether to move schools as they fall due or to align them. A phased move spreads risk; an aligned move gives the trust one data model sooner.
The briefing settled some practical points as well. Using the framework does not require a change of supplier. Framework prices are maximums, so a trust that has negotiated a better price should expect to match it through a direct award. Third-party support providers are outside the framework, and schools are not expected to buy support from their MIS supplier.
Renewal planner
One row per school. Everything stays in this browser; nothing is stored or sent.
0 of 1 school ends before launch.
Add the contract end date to see the rule, notice deadline and stage dates.
Columns in this order: school, supplier, end date, notice months, extension (yes or no). Tab or comma separated.
| School | Supplier | Ends | Situation | Notice deadline | Requirements | Procurement | Data preparation | Migration | Training | Census |
|---|---|---|---|---|---|---|---|---|---|---|
Add a contract end date to see the timeline.
Working backwards
DfE has not published lead times, and every trust's will differ. As a working assumption to adjust, a move runs through five overlapping stages.
- Requirements and governance: what the trust needs, who signs off, what the board must see.
- Procurement: a call-off from the framework, or a transitional contract with the Core Principles written in.
- Data preparation: cleansing, field mapping and agreeing what moves.
- Migration and integration: moving records, reconnecting third-party tools and testing statutory returns.
- Training and settling in: office, data and teaching staff, with a period of running in parallel.
Two constraints narrow the window. Notice periods can fall due months before the end date. And the autumn, spring and summer census returns are the worst moments to be mid-migration.
What moves to DfE, and what stays
The framework moves work from 22,000 schools to one department, which describes it as giving schools their "collective buying power6". Suppliers are vetted and terms written once, with prices capped. Small trusts without procurement teams gain most.
The decision about what a trust needs stays with the trust. Those that use the next eighteen months well will have finished their planning before the first renewal date arrives.